Map of temporary traffic adjustment at Highway 210/Redwood Lane intersection. (MnDOT)
FERGUS FALLS, Minn. (KFGO-KBRF) – Crews have been working to get the concrete complete along the new alignment and other final touches in preparation for the next phase of traffic changes on Highway 210.
MnDOT is anticipating east/west traffic will move to the new Highway 210 alignment and bridge on Thursday, September 17. At that time, the northside ramps (eastbound I-94 off-ramp and westbound I-94 on-ramp) will reopen as well. That date is subject to change, based on weather and concrete progress.
The intersection at Redwood Lane will have temporary lanes constructed to connect the new alignment with the old alignment, so traffic can continue to flow while crews complete the west leg of the roundabout at Redwood Lane.
And starting Monday, weather permitting, I-94 traffic will run head-to-head to allow crews to finish up work underneath the bridge.